Each question shows where it is from (session, paper and question number, or the book), the section it tests, and whether it is Core (Paper 1/3) or Extended (Paper 2/4). Choose an answer for each question, tap Check my answers to mark that part, then Show solutions to see the working. Your best score is saved on this device.
APart A 9 questions
Questions 1โ9.
A person carries 20 tiles, each of mass 1.2 kg, from the ground up to a roof 15 m above the ground. How much work is done against gravity on the tiles?
- Stepmass = 20 ร 1.2 = 24 kg
- Stepweight = 24 ร 9.8 = 235 N
- Stepwork = 235 ร 15 = 3530 โ 3500 J
- C360 J uses the mass (24 kg) instead of the weight.
- B180 J is one tile's mass ร 15 ร 10.
- A37 J divides by g (24 ร 15 รท 9.8) instead of multiplying.
As an object falls freely, energy goes from its gravitational potential store to its kinetic store. How is it transferred?
The gravitational force does work on the object as it moves downwards: energy is transferred mechanically (by a force acting through a distance).
A frictional force of 30 N brings a moving object to rest over 5.0 m, transferring energy from its kinetic store to an internal store. How much energy is transferred, and how?
- StepW = 30 ร 5.0 = 150 J
- Stepa force moving through a distance = mechanical working
In a mobile (cell) phone, energy goes from the chemical store of the battery to the internal (thermal) and kinetic stores, and out as heating and sound. How is the energy transferred from the chemical store?
The batteryโs chemical store is emptied by an electric current in the circuit: energy is transferred by electrical work. The electrical energy then heats parts of the phone, moves the speaker cone (kinetic) and makes sound.
A force does work moving an object in the direction of the force. Which change always increases the work done?
A greater force over the same distance always gives more work. With a smaller distance, the result could go either way.
A horizontal force pulls a box along a surface. The box gains 30 J of kinetic energy and 10 J of thermal energy is produced by friction. How much work does the force do?
All the work done by the force is transferred: 30 J of kinetic energy + 10 J of thermal energy = 40 J.
In which unit is work done measured?
Work done = force ร distance = energy transferred, so it is measured in joules (1 J = 1 N m).
Which statement is correct?
- A, Benergy is not "per unit time"; it is power ร time.
- Dpower is energy รท time, not time รท energy.
A man pushes a box 4.0 m along the floor with a force of 40 N, taking 3.0 s. What power does this need?
- Stepwork done = 40 ร 4.0 = 160 J
- StepP = 160 รท 3.0 = 53 W
BPart B 8 questions
Questions 10โ17.
What is the unit of power?
Power is measured in watts (W): 1 W = 1 J/s.
A pump does 460 000 J of work raising water to fill a tank, which takes 7 minutes. What is the power of the pump?
- Stept = 7 ร 60 = 420 s
- StepP = 460 000 รท 420 = 1095 W โ 1.1 kW
The power of a machine is increased. Statements: 1 โ the work done in a given time decreases; 2 โ the work done in a given time increases; 3 โ the time to do a given amount of work decreases; 4 โ the time to do a given amount of work increases. Which are correct?
More power means more work in a given time (2), so a given job is done in less time (3).
A weightlifter lifts a stone ball onto a shelf, each lift taking the same time. A: large ball, low shelf. B: large ball, high shelf. C: small ball, high shelf. D: small ball, low shelf. Which lift needs the greatest power?
Every lift takes the same time, so the greatest power needs the most work: the heaviest ball raised to the highest shelf.
A man pulls a truck 20 m in three different ways. The slopes are all the same.
1 20 m up the slope. 2 10 m up the slope, then 10 m along level ground at the top. 3 10 m along level ground, then 10 m up the slope.
Which statement about the work done against gravity is correct?
Work done against gravity = weight ร vertical height gained. Route 1 is uphill for both sections, so it gains the most height. Routes 2 and 3 each have one uphill section, so they gain the same height.
- Broute 3 still has an uphill section, so work is done.
- Croutes 2 and 3 involve equal work against gravity.
- Droute 1 gains twice the height of route 2.
An object has 200 J of kinetic energy. A constant resultant force of 190 N then acts on it in its direction of motion for 10 m. What is its final kinetic energy?
- Stepwork done = F ร d = 190 ร 10 = 1900 J
- Stepthis is added to the kinetic energy: 200 + 1900 = 2100 J
A woman pushes a 25 kg pram up a slope with a force of 150 N along the slope. The slope is 20 m long and rises 10 m. Take g = 10 N/kg. How much of the work she does is wasted as thermal energy?
- Stepwork done by her = 150 ร 20 = 3000 J
- Stepgain in GPE = 25 ร 10 ร 10 = 2500 J
- Stepwasted = 3000 โ 2500 = 500 J
An engine transfers 240 kJ of energy in 2.0 minutes. What is its power output?
- StepP = 240 000 J รท 120 s = 2000 W = 2.0 kW